Opal Tower residents could wait months before repairs are finished

| 23.02,19. 07:08 PM |


Opal Tower residents could wait months before repairs are finished


Photo: Shady Eskander from the owners corporation has called for a detailed management plan. (ABC)


The owners corporation behind the Opal Tower says it has "many questions" to be answered before it approves a plan by the builder for repairs on the damaged building — meaning residents could be homeless for months.


Icon, the builder of the 36-storey apartment complex evacuated on Christmas Eve after residents heard a loud cracking noise, told the ABC it expected remediation works on the tower to take another "four to six weeks".


However the Opal Tower owners corporation — which has employed an independent engineer to asses the building — needs to give Icon the green light before any repairs can occur.


The owners corporation, headed by resident Shady Eskander, said it was committed to ensuring all decisions were made with "a proper process", and called for a detailed management plan to be developed.


It means residents face a continued wait before they can return to their homes, which could potentially stretch well beyond the two-month mark.


The move came after the NSW State Government yesterday released its final report into the building, following a near two-month investigation.


The report found problems caused by changes made after the original Opal Tower design were exacerbated by "construction issues", with "lower-strength concrete" and "under-designed" critical support beams bursting under extreme pressure.


Icon confirmed 259 units in the 392-unit apartment complex at Sydney's Olympic Park are today still empty, with hundreds of families still in temporary accommodation.


Many have vowed never to return.


In a statement, Icon told the ABC it "welcomed the Government's findings" and believed the construction-related issues identified in the report had been "satisfactorily addressed".


"Icon is performing remediation work in seven areas of the building: two areas on level 4, two areas on level 10 and three areas on level 16," the company said.

"Remediation plans have been finalised and issued to the body corporate (owners corporation) for consent which Icon hopes will be provided without delay, as recommended by the report."

"Once consent is given, Icon anticipates the works will take approximately four to six weeks to complete.

"Icon is ready to undertake these works immediately."

The Opal Tower owners corporation said it had been actively seeking more information from all parties since the date of the incident.

"[We] have only received initial remediation plans eight weeks after the incident on Christmas Eve," it said in a statement.

"All residents are eager to return home but [we have] many questions that have arisen and need to be addressed with Icon in order for approval to be provided."

"As the NSW Government has also just released their findings, the owners corporation must digest all information provided, and would only issue approval to commence remediation after taking into consideration the independent opinions of all experts involved."



In the meantime, experts have warned of an "Opal Tower" effect causing a "feeding frenzy of negativity" in the off-the-plan apartment market.


Some residents have openly questioned whether they will ever be able to sell their apartments, some of which were originally valued at $2.5 million.


Ecove, the developer behind the project, said it welcomed the report on the building's faults. It described the process as "devastating".


"It is extremely concerning to have it confirmed again in this final report that changes made after the original design and exacerbated by construction issues appears to lie at the core of the problem," Ecove said in a statement.


"Ecove supports any initiative to ensure the integrity of the design and construction process, and return confidence to the community and to the building and construction industry."

abc



(Votes: 0)

Other News

Canberra Aeronautical Club member hospitalised after NSW plane crash Ballarat police officer found guilty of assaulting woman in custody escapes conviction Townsville man charged after flood-ravaged homes in Idalia stripped of $80,000 in goods Woman found with life-threatening head injury on Gold Coast driveway Opal Tower builders used lower-strength concrete, beams burst under pressure Cyclone Oma weakens but impacts still expected along Queensland coast Sydney nurse Anita Cobby's killer Michael Murphy dies in Long Bay jail Australian retailers shut down by foreign competition Class action filed against Westpac could affect thousands of Australian home loans Cyclone Oma to bring gale-force winds but may not cross Queensland coast, BOM says Carpet python devours currawong on roof in viral video Plan to tackle chronic lung conditions Tropical Cyclone Oma could make it to the Queensland coast early next week, BOM says Search for backpackers Hugo Palmer and Erwan Ferrieux scaled back at Shelly Beach ‘PROPERTY BLOODBATH’: House prices ‘could fall by half’ in horror decline Government’s sixth annual wastewater testing shows Aussies spend $9.3 billion on illicit drugs WA schools resort to bans on playground games and sport to combat early student drop-offs Bushfire emergency: Warning for Balingup and homes threatened near Nannup, Bridgetown Man critical after train station attack Fears for two backpackers missing from NSW north coast beach Rent looms as key election issue as government attacks ‘big new housing tax’ This image shows likely wave heights on Friday approaches Queensland Ex-police officer avoids jail time after sharing explicit photos of arrested woman Sydney is expensive, but what people spend their money on might surprise you Ex-NSW policeman 'blackmailed victims into sex' 'Out of character': Man killed in home invasion was champion body builder Major parties hit by foreign government hackers in attack on Parliament servers Woolworths to stop selling $1 milk in win for dairy farmers Muslim association in Vienna provides food to homeless Federal Government probed over awarding of Manus Island security contracts to Paladin Group